Under what circumstances might you wish to crash a project?
Crashing may be desirable if
initial time estimates are inaccurate, the project falls behind schedule or the
project completion date is moved up.
In these cases, the project cannot be completed on time given the
original schedule. Crashing would
expedite the project/activities to meet new completion dates. Another scenario occurs when late fees
or penalties may be incurred. It
may be more cost effect to crash activities than to pay the additional fees.